Construction of the Brazil facility begins in Jaguariuna
Wednesday, February 08, 2012 - Gothenburg.
The Brazil facility, which is expected to be fully built by July of this
year,
began to be constructed last week in Jaguariuna. Trucks began to remove
the grass and leveling the earth on the site. Construction is expected to fully
begin by the end of February.
The facility, estimated to be fully operational
in October, will have around 30 employees in the beginning and will start by
assembling radiators and charge air coolers with imported material from Mjällby
and other local Brazilian suppliers.